Pile testing Cologne

Pile testing in Cologne

Load testing and integrity testing for Cologne, Bonn and the Rhineland. Own measurement technology, test force up to 40,000 kN, travel distance about 3.5 hours from Gotha.

Ground conditions

What Cologne is founded on.

Rhenish terrace gravel over tertiary sands and clays, in the surrounding area loess and lignite open-pit mining with dumps and large-scale groundwater lowering. Rising groundwater changes the stresses in the ground over decades.

What happens without testing

On dumps and in lowering cones, experience values are worthless because the ground no longer has a naturally grown profile. Settlement occurs there with delay, often years after acceptance.

Untested foundations are not a cost risk, they are a structural stability risk. Differential settlement, cracking and re-foundation cost many times the price of testing.

Typical construction tasks: Commercial and logistics construction, transport structures, building on dump areas, existing building protection in old town locations.

Methods

Three methods, one decision.

In Cologne, Bonn and the Rhineland the ground often leads to dynamic load test. We make the final choice based on the ground report and pile concept, not on instinct.

Dynamic load test in Cologne

Bearing capacity of several piles within one day, evaluated per CAPWAP. The method per DIN EN ISO 22477-4 delivers shaft friction and base resistance separately and fits where the construction schedule does not allow a week of setup.

Drop weight up to 12 t, evaluation per CAPWAP

Static load test in Cologne

The direct proof per DIN EN ISO 22477-1. The load-settlement line shows the real load behaviour under sustained load, up to 40,000 kN test force. Basis for foundation optimisation and for any disputed proof.

Up to 40,000 kN, own loading platform and beam system

Integrity test in Cologne

Test of construction quality: length, cross-section, necking, defects. Low-strain from the pile head for the whole site, cross-hole between measuring tubes for the core of large bored piles.

Low-strain and cross-hole, large quantities

Regional answers

Questions on pile testing in Cologne

All questions on process, methods, standards and scheduling are in the FAQ section.

Pile testing in Cologne

A soil survey and pile concept are enough for a reliable answer. Travel distance about 3.5 hours from Gotha.

Project inquiry

Request a project

Tell us the project, the number of piles and the planned test load. You will receive a test concept with a quote within two business days.